System Integration / For safety designers

Activation Regime Table: How to Plan It and What You Need

An activation regime table sets out what each detector in the building triggers. The table is prepared by the safety designer and becomes part of the building's safety plan. Here's how it is done, what is needed to prepare it — and where we come in.

What the service includes

What you need to prepare the table

01

The building's safety plan

The fire safety annex submitted for the permit: fire compartments, escape routes, protected stairwells and the required detection and suppression systems.

02

List of participating systems

Every system that responds to an event: lifts, smoke control and pressurization, air conditioning, power and generator, fire doors and shutters, PA, sprinklers and gas suppression.

03

Zones and uses

How the building is divided into detection zones and smoke zones, and what each zone is used for — offices, assembly, parking, technical rooms.

04

Electrical data

Which panels are disconnected in an event and which keep running on the emergency supply, and where the firefighters' control panel is.

05

Engineering analysis, if required

In buildings with a computerized smoke analysis (CFD), the smoke control regime follows its results, and every deviation is marked in the table.

06

Interface details for each system

Which signal each system receives from the panel and which feedback it returns — data that comes from the contractors and installers.

How we work

From the plan to the table, and from the table to the test.

The order in which the activation regime table is built and tested, under Directive 536.

  1. Studying the building

    Uses, ceiling heights, fire compartments and the safety systems required by the permit.

  2. Choosing the response to each event

    For each type of detector and zone: what is triggered by the first detector, what by the second, and what only manually.

  3. Preparing the table

    Event rows, response columns, clarifications and timings — one document attached to the safety plan.

  4. Programming and connection

    The installer programs the panel and connects the systems according to the table, and carries out a preliminary test.

  5. Testing and approval

    The Standards Institution or a recognized laboratory tests the building against the table and issues an approval.

The table stays with the building

A change in one system changes the table.

The approved activation regime is part of the building’s safety plan, and it remains valid as long as no change is made. Replacing the panel or changing a system that takes part in the integration requires updating the table and re-testing the installation.

Who prepares an activation regime table, and what it includes

An activation regime table, also called an integration table, is the document that sets out how each system in the building responds when the fire detection system or an automatic suppression system detects an event. Fire and Rescue Commissioner’s Directive 536 sets the basis and the defaults, but the exact sequence is decided for each building separately, according to its use and the designer’s engineering judgement.

Who may plan the activation regime

The directive places the planning on the designer: the main permit applicant, a secondary applicant, or a fire safety designer appointed by the main applicant. In practice this is usually the project’s fire safety consultant or designer. The designer is responsible for the activation regime in consultation with the Fire and Rescue Authority, and may add to the table components required for the proper operation of the emergency systems — as long as there is no conflict with the directive.

A safety officer can prepare the table when he is also the project’s fire safety designer. Otherwise he — like the maintenance manager and the installers — is an important partner in gathering the data, in the tests and in keeping the regime over the years.

How the table is built

The rows list the events — what triggered the system and where. The columns list the response of each system. Below the table come clarifications: timings, exceptions and conditions.

Event (row) Example responses (columns)
First detector in office areas Sounders and beacons according to the verification mechanism
Second detector or sprinkler flow Evacuation PA, lifts to the designated floor, air conditioning stopped, smoke extraction, fire dampers closed
Detector in the intake duct of a pressurization fan Fan stopped and smoke vents opened at the top of the stairwell
Detector in a protected stairwell Smoke vents opened at the top of the stairwell, and the pressurization fan keeps running
Detectors in an electrical room with gas suppression Suppression released, light and “suppression activated” sign at the entrance
Suppression in a commercial kitchen hood Energy sources to the cooking line disconnected

The examples are based on the clarifications in the directive. Every building gets a table of its own.

Decisions the designer needs to make

  • Verification mechanism — whether the building’s use allows a delay for verification before the sounders are activated, under Commissioner’s Directive 550.
  • Lifts — where each lift is sent when the event is in the entrance lobby and when it is on another floor, and how the firefighters’ lift operates.
  • Smoke control — in spaces higher than 4.5 meters, in warehouses and in industry, activation is manual or after the sprinklers operate; with ESFR sprinklers — manual only.
  • Power disconnection — which panels are disconnected, while the generator panel, the smoke and pressurization fan panels and the fire pump panel keep running.
  • Special buildings — in hospitals, CBRN-protected buildings and security facilities, the regime is also coordinated with the relevant bodies.

After the table is ready

In a building with mixed uses, the activation sequence is submitted to the Fire and Rescue Authority together with the fire safety plan or annex. The detection panel is programmed and the systems are connected according to the table, and finally the Standards Institution or a recognized laboratory tests the building against it. In an existing building, the periodic test is carried out against the original regime — and the preparation for the integration test relies on it as well.

Where we come in

We do not prepare the activation regime table — that is the designer’s job. We work alongside the designer: providing data on the detection system and the emergency PA, making sure the interfaces in the table are feasible on site, programming the panel according to the table, and carrying out a preliminary test before the official one.

A microphone station for zone-based announcements (illustration)

Frequently asked questions

Frequently asked questions about the activation regime table

What is the difference between an activation regime and an activation regime table?

The activation regime is the way the building’s emergency systems operate together. The table is the document that describes it, row by row — and the panel is programmed and the building tested according to it.

Can a safety officer prepare the table?

Under Directive 536, the activation regime is planned by the designer: the main permit applicant, a secondary applicant or a fire safety designer appointed by the applicant. A safety officer who fills one of these roles in the project can prepare it; otherwise he takes part in gathering the data and in the follow-up.

When does the table need to be updated?

With any change to a system that takes part in the integration, when the panel is replaced, and when the building’s use or layout changes. After the update, the installation must be re-tested.

Is there an official template for the table?

Directive 536 includes a general table with event rows for common uses, and clarifications for each response. The designer adapts it to the building and adds components as needed.

What do you need from the designer to program the panel?

The table, the zone plan and the list of interfaces for each system. Before programming we go over it together with the designer, to make sure every row is feasible on site.

Are you planning an activation regime for a building?

We'll be happy to go over the table with you, check the interfaces on site and program the panel according to it.

Contact us on WhatsApp →
WhatsApp